How long does planning permission take?

For a householder application in England the council should decide within 8 weeks of receiving a valid application. Plan for 10 to 14 weeks from first submission for a straightforward scheme, and 3 to 6 months from the start of design to a start on site for a heritage project. Here is where the time goes and what you can control.

The law: Town and Country Planning Act 1990, sections 78, 91 and 92; DMPO 2015, articles 34 and 37; GPDO 2015, Schedule 2, Part 1, A.4; planning guarantee. Sources last reviewed in November 2026.

In this guide
  1. Statutory periods by application type
  2. Extensions of time, and the 16 and 26 week backstops
  3. Outline permission and reserved matters
  4. Permitted development and prior approval
  5. The stages, in order
  6. Why applications run over
  7. Realistic timelines: worked examples
  8. How to keep your application on time
  9. If the answer is no, or no answer comes
  10. After the decision
  11. Questions readers ask

Statutory periods by application type

The time a council has is set by article 34 of the Development Management Procedure Order 2015 and, for prior approvals, by the GPDO itself. The clock starts the day after a valid application arrives.

How long the council has to decide, England, November 2026
ApplicationStatutory periodFee from 1 April 2026
Householder planning permission8 weeks£548
Listed building consent8 weeksNo fee
Other minor applications (for example one new house)8 weeksSet by the fee schedule
Major development (10 or more homes, or 1,000 m² or more)13 weeksSet by the fee schedule
Any application with an Environmental Impact Assessment16 weeksSet by the fee schedule
Outline permission, then reserved matters8 or 13 weeks for each stageEach stage is a separate application
Lawful development certificate, proposed8 weeks before an appeal is possible£274
Certificate of lawfulness of proposed works to a listed building6 weeks before an appeal is possibleNo fee
Prior approval, larger rear extension42 days; you may build if no decision arrives£249
Prior approval, demolition (GPDO Part 11)28 daysSet by the fee schedule
Discharge of conditions8 weeks£89 for a householder permission
Non-material amendment28 days£46 for a householder permission
Building regulations, full plans (separate system)5 weeks, or 2 months if you agreeSet by each council

"Valid" is the word that matters. If a required document is missing, the council can declare the application invalid and the period does not begin until the gap is filled. Most householder schemes on old houses are 8 week cases; the 13 and 16 week periods matter if your project is part of a bigger development, and they explain why a neighbour's scheme for flats can take far longer than your extension.

Extensions of time, and the 16 and 26 week backstops

If a council needs longer, it can ask you to agree an extension of time. The agreement must be in writing and give a new date. You can say no. If you do, the officer decides on what is in front of them, which on a heritage scheme that still needs amending usually means a refusal. Where the request is to allow changes that will make the scheme acceptable, agreeing is nearly always the better trade.

Government policy adds a backstop called the planning guarantee: no application should take longer than 16 weeks for non-major development or 26 weeks for major development unless a longer period has been agreed. If a non-major application is still undecided after 16 weeks, no longer period has been agreed and you have not appealed, government guidance says the fee is refunded. Deliberately stalling to earn a refund is a bad idea: it counts against you if the case later goes to appeal.

Outline permission and reserved matters

Outline permission settles whether development is acceptable in principle and leaves some or all of access, appearance, landscaping, layout and scale to be approved later as reserved matters. It is rarely used for householder work but common for a new house in a garden or on a plot. Under section 92 of the 1990 Act the default is that reserved matters must be applied for within 3 years of the outline permission, and work must begin within 2 years of the final reserved matters approval. Each stage has its own 8 or 13 week period, so an outline route usually takes at least twice as long as a full application.

Permitted development and prior approval

Work that is permitted development needs no application at all, so there is no waiting time, only the time to design it properly. Some classes need the council's prior approval first. The best known is the larger rear extension: the council notifies neighbours, gives them 21 days, and has 42 days from receiving your notification. If it has not decided by day 42, you may build what you described. Demolition of a building under Part 11 has a 28 day period. Neither applies in a conservation area in the same way; check the conservation area rules.

A lawful development certificate is not required for permitted development, but owners who want proof usually apply for one first, which adds about 8 weeks. See lawful development certificates.

The stages, in order

  1. Pre-application advice (optional, 4 to 10 weeks). For listed buildings and sensitive conservation area schemes, worth the time. Councils set their own fees and timescales. A meeting on site with the conservation officer is the most useful kind.
  2. Preparing the application (2 to 8 weeks). Survey, drawings, heritage statement, ownership certificate, and any specialist reports the council's local validation list asks for, such as a tree survey or flood risk assessment.
  3. Validation (a few days to several weeks). The council checks the application is complete and registers it. Validation backlogs vary hugely: some councils validate within 3 working days, others take two or three weeks even for complete applications.
  4. Consultation (21 days). Neighbours are notified by letter or site notice and get at least 21 days to comment. For listed buildings and conservation areas the council also publishes a press notice and site notice, each with 21 days.
  5. Assessment and site visit. The case officer visits, reads the comments and consults the conservation officer. This is where requests for amendments arrive, typically in weeks 4 to 6.
  6. Decision (target week 8). Most householder applications are decided by officers under delegated powers. Applications attracting a set number of objections, or called in by a councillor, may go to committee, which can add a month or more.
  7. Conditions (4 to 10 weeks after the decision). Heritage permissions commonly require approval of materials, joinery details or a method statement before work begins. Each submission has an 8 week period of its own.
Drawings of a rear extension laid out on a desk with a scale rule, pencil, brick samples and slate
Drawings and samples on the desk

Why applications run over

The 8 week target is met for most householder applications in England, but heritage cases are over-represented in the ones that are not. The usual causes are:

  • Invalid on submission. Missing heritage statement, wrong ownership certificate, drawings without a scale bar or north point, or the wrong fee. Each round of correction costs one to three weeks.
  • Design amendments. The officer will often support a scheme subject to changes, for example reducing a dormer or changing a window pattern. Rather than refuse, they ask for an extension of time to receive revised drawings, and may re-consult neighbours for 14 or 21 days.
  • Consultee responses. For Grade I and II* buildings, Historic England's advice adds time. Specialist consultees such as tree officers and highways can be slow.
  • Committee. Contentious schemes go to committee, which meets monthly in most councils.
  • Workload. Some councils, especially in London, carry significant backlogs, and extensions of time are routine.
Statutory does not mean guaranteed

The 8 week period is a target the council should meet, not a promise. If it passes without a decision and without an agreed extension, you can appeal to the Planning Inspectorate for non-determination. In practice that route is slower than waiting. The planning guarantee gives a fee refund if a householder application made since 6 December 2023 is still undecided after 16 weeks without an agreed extension.

Realistic timelines: worked examples

Rear extension in a conservation area, unlisted house

Drawings ready, no pre-application advice. Submitted 2 November 2026, validated within a week. Consultation closes late November. The officer asks for a slight reduction in height in mid-December; revised drawings take a week and the council asks for a two-week extension. Decision mid-January 2027: about 11 weeks. A materials condition adds 5 weeks before work starts.

Internal alterations and a rear dormer to a Grade II terrace

Pre-application meeting with the conservation officer takes 7 weeks. Drawings revised in 2 weeks. Combined planning and listed building consent applications submitted, validated in 10 days. Consultation and press notice run 21 days. One round of amendments. Decision at about 12 weeks. Conditions on joinery details take another 6 weeks. From first contact with the council to start on site: about 27 weeks.

Larger home extension, 5 m deep, not in a conservation area

Prior approval notification submitted 2 November 2026. The neighbour is notified and does not object. The council issues "prior approval not required" on day 35. If it had not responded, the owner could start on day 43. Total: about 6 weeks, with no conditions to discharge.

Model your own case with the planning timeline estimator, which builds a dated programme from these stages.

How to keep your application on time

  1. Read the council's local validation list before preparing anything. It tells you exactly what documents are needed for listed buildings and conservation areas.
  2. Include a proportionate heritage statement even for minor works. It is the most common reason for heritage applications being made invalid.
  3. Get the ownership certificate right. If anyone else owns any part of the land, including a freeholder for a flat or a neighbour where foundations cross the boundary, serve notice and use Certificate B.
  4. Submit large-scale details up front for windows and doors in heritage cases. It can avoid a condition and saves weeks later.
  5. Talk to neighbours first. Objections do not decide applications, but they can push a case to committee.
  6. Respond quickly to requests. A same-week response to an amendment request often avoids an extension of time.
A Georgian six-panel front door painted dark green, with a fanlight above, stone steps and iron railings
A six-panel door and radial fanlight

If the answer is no, or no answer comes

You can appeal to the Planning Inspectorate under section 78 of the 1990 Act. The deadlines for applications made on or after 1 April 2026 are:

  • Refusal of a householder application: the Inspectorate must receive the appeal within 12 weeks of the decision notice.
  • Council fails to decide a householder application: within 6 months of the end of the period it had to decide.
  • Conditions you object to on a householder permission: within 6 months of the decision.
  • Refusal of listed building consent and most other applications: within 6 months.

Most householder appeals are decided on written evidence, and many take several months. A revised application that answers the reasons for refusal is often quicker, and a resubmission within 12 months of a refusal for similar development by the same applicant usually costs nothing.

After the decision

A householder permission usually lasts three years from the decision date; work must have begun by then. Listed building consent has the same default period. Before work starts, check that every pre-commencement condition has been discharged in writing. Starting work in breach of a pre-commencement condition can leave the whole development unauthorised.

Planning permission is only one of the clearances needed. Building regulations approval, party wall notices (one month's notice for excavation near a neighbour's foundations, two months for work to a party wall) and, for leasehold flats, the freeholder's consent all need to fit into the programme.

Questions readers ask

How long does planning permission take for an extension?
The target is 8 weeks from a valid application. Allow 10 to 14 weeks from submission in practice, plus time before submission to prepare drawings.
Can I start work before planning permission is granted?
You can, but at your own risk: if permission is refused, the council can require the work to be removed. Never start work to a listed building without consent; that is a criminal offence.
How long does listed building consent take?
The same 8 week target. Grade I and II* cases often take longer because Historic England is consulted.
How long is planning permission valid for?
Normally three years from the date of the decision unless the permission says otherwise (section 91 of the 1990 Act). Work must have lawfully begun within that time; once it has, the permission does not lapse if building pauses.
How long does it take for plans to be approved?
Planning permission for a householder scheme: 8 weeks from a valid application, 10 to 14 weeks in practice. Building regulations plans are a separate approval: building control should decide a full plans application within 5 weeks, or 2 months if you agree.
How long do I have to build after planning permission?
You must start within the time the permission sets, normally three years. There is no general deadline to finish, though a council can serve a rare completion notice on a stalled scheme. For outline permission, start within 2 years of the last reserved matters approval.
What is the 10 year rule in planning?
For building work in England substantially completed on or after 25 April 2024, the council has 10 years to take enforcement action; after that the work becomes lawful and a section 191 certificate can confirm it. Work completed before that date had a 4 year limit. There is no time limit for unauthorised work to a listed building.

Where we checked