How long will it take? A planning timeline for your project

Choose the application and the date you hope to submit. The timeline lays out each stage in order, from pre-application advice and validation to the decision, conditions and a realistic first day on site.

Figures used

Statutory periods and the typical ranges built into the estimator
StageFigureBasis
Householder planning permission8 weeks (56 days)Statutory period for non-major applications, DMPO 2015 article 34
Listed building consent8 weeksStatutory period; no fee
Lawful development certificate8 weeksPeriod after which you can appeal for non-determination
Certificate of lawfulness of proposed works (listed)6 weeksAppeal right after 6 weeks; no fee
Prior approval, larger home extension42 days from receiptGPDO Part 1 Class A, A.4(10); you may build if the council has not decided
Demolition prior approval determination28 daysGPDO Part 11 Class B, site notice for 21 days
Consultation21 daysMinimum for neighbour notification, site and press notices
Validation (complete)3 to 10 daysTypical registration time; the clock still runs from receipt
Validation (missing items)14 to 42 daysTypical; the period runs from when the application becomes valid
Pre-application advice4 to 10 weeksTypical council service levels; not statutory
Discharge of conditions4 to 10 weeksStatutory period is 8 weeks; householder fee £89

How the estimator calculates

Every stage is added as whole calendar days to a range with a lower and an upper bound. The lower bound uses the quickest typical figure at every stage; the upper bound uses the slowest. The two are carried through the programme separately, so the final window is the sum of the best and worst cases, not an average.

Statutory periods count from the day after the council receives a valid application, which in practice is very close to the submission date for a complete application. Where items are missing, the estimator restarts the period from the validation date. Extensions of time are added after the statutory target and are not applied to prior approval or demolition determinations, because those have fixed deemed-consent deadlines.

Worked example

Householder application for a rear extension in a conservation area, submitted on 2 November 2026, complete, no pre-application advice, extension of time possible, conditions expected. Target: 2 November + 56 days = 28 December 2026. With up to 28 days' extension, the decision window is 28 December 2026 to 25 January 2027. Discharging conditions adds 28 to 70 days, so a realistic start on site is late January to early April 2027, before allowing for party wall notices and builder availability.

Targets, not promises

Statutory periods are what the council should achieve, not what it guarantees. Your main remedy for delay is an appeal for non-determination, which is usually slower than waiting. There is a backstop: under the planning guarantee, the council must refund the planning fee if a householder application made since 6 December 2023 is still undecided after 16 weeks, unless you agreed a longer period in writing or have already appealed.

The full explanation, with the reasons applications slip and what you can control, is in how long planning permission takes. To work out which application you need in the first place, use the consent check.